Pilot Site Characteristics and Historical Baseline Data
As mentioned, the building selected for the demonstration is a 100,000 sqft office building at 160 Sansome Street in San Francisco, also known as the Hong Kong Bank Building. The building is about 30 years old, with two 200-ton chillers that are also 30 years old. Additional facts about the building characteristics and operating patterns are described in Table 41 below in reference to changes in energy use over time.
Table 41. Building Characteristics and Features
| Building Size | 100,000 sqft |
| Chillers | Two @ 225 tons each (centrifugal), 0.8 kW/ton at full load |
| Cooling Towers | Two-cells, 20 hp each |
| Air Handlers | 100hp Supply Fan w/VFD; 75hp Return Fan w/VFD; both at 100,000cfm |
| Space Heating | Purchased steam |
| Controls | 286 PC pnuematic system with limited automation of central plant; some occupancy sensors |
| HVAC Distribution | Combination of CV and VAV systems |
| Lighting | Combination of T-12 and T-8 lamps |
In order to understand the current energy use and potential savings it is necessary to obtain historical energy use data. We also collected other whole-building energy use intensities to compare this building with others of its type. The historical data are needed to develop a baseline to evaluate changes in energy use that may result from the use of the IMDS. The data collected for the baseline analysis include:
The data collected and presented are limited to energy use data
at the request of the property manager. We do not include energy costs
or rates.
Whole-Building Energy Use Comparison Data
Figure 41. Annual Site Energy
Use (kBtu/sqft-yr) of Demonstration Site
and Comparison Buildings
|
|
|
|
Other Comments |
|
|
|
|
|
|
|
|||
|
|
|||
|
|
|
|
Lower occupancy after construction. Relatively cool weather year. |
|
|
|
|
|
|
|
|
|
Large kitchen removed |
|
|
|
||
| * Occupancy figures are general
estimates made by the building operator.
** Construction involved complete gutting of interior and asbestos removal. Lighting retrofits were also completed, replacing F40/T12 lamps with T8. |
|||
IMDS Use and Findings Logsheet
Figures 44 and 45
show seasonal trends in energy consumption from historical data (not the
IMDS). Figure 44 shows six years of data
for each month of the year. Figure 45
shows the average monthly energy use over the six-year period. We see very
little change in electricity usage over the year. One might expect an increase
in electricity use during warmer months from cooling energy. We do, however,
see some temperature sensitivity of electricity use at the daily level,
as further discussed below. Steam follows the pattern one expects, with
increased usage during colder months when more heat is required.
Figure 46 shows the hourly electric
load profiles for about three months (June 19 through September 30, 1997).
The load profiles show that the building is extremely regular in its usage
pattern. Nighttime energy use is extremely low. All HVAC systems and most
equipment tend to be off at night, with HVAC coming on at about 6AM. Although
we do not yet have end-use data, there appear to be four distinctive day-types
that can be easily identified. First, weekends and holidays are days with
low power similar to nighttime power. (There are few nighttime and weekend
occupants; after-hour HVAC services are available at a relatively high
price.) Next, there appear to be typical workdays that are those when the
chillers are not needed. The next higher load shape represents days when
one chiller was used. Finally, the highest power days are those when both
chillers are used. These days correspond to the periods with the warmest
weather.
The highly regular and well-controlled building systems suggest that
basic equipment scheduling will not be where we will find energy savings.
Rather, we expect that the IMDS can be used to improve chiller and cooling
tower control. We will only explore these changes after we first give the
on-site staff time to use the system without our intervention. The current
outdated EMCS, unlike most for this type of building, does not provide
any information about the chilled water supply temperature or condensing
water temperature. We also expect that the overall cooling plant has poor
efficiency (high kW/ton). We provide some examples here of the opportunities
for improving the cooling tower performance. The cooling towers are blow-through
towers with centrifugal fans, which are inherently inefficient. We will
consider the savings possible with a variable frequency drive for the tower
fans. We will examine the general conditions of the cooling tower, such
as the fill water treatment and airflow rate. We will consider alternatives
to the current cooling tower operation, such as changing the fill or water
treatment, or perhaps increasing the louver area. Another possibility might
be to increase the condenser flow by removing obstructions (such as the
strainer, globe and balancing valve, and orifice plates, etc.) and possibly
running two pumps to one chiller.
Weather Data and Regression Analysis
The relationship between electricity consumption and outside air temperature
is a useful characteristic of the buildings energy use profile, and will
serve as a model for evaluating changes in energy use from use of the IMDS.
Daily average outside air temperature data were obtained from a nearby
National Weather Service weather station through a public domain web site
(Kissock, 1998). We condensed three months of half-hour data into daily
averages. A regression of hourly temperature data against energy use is
problematic because it is affected by autocorrelation. That is, the temperature
in one hour is heavily dependent on the temperature during the previous
hour. There is some auto-correlation in daily temperature data as well,
but it is not as significant. See Piette et al, 1997 and Ruch et al, 199x
for further discussion of this issue.
Two linear regressions, one for weekends and the other for weekdays,
were developed using an analysis tool from researchers at Texas A&M
known as Emodel (Kissock et al, 1994). (Weekday and weekend energy use
are dramatically different, as shown in Figure
46 above.) EModel was designed to integrate data processing, graphing,
and modeling of building energy use data to determine baseline energy consumption
and calculate retrofit savings, supporting simple linear and change-point
regression models. Results are shown in Figure
47. The upper regression line represents weekday usage and the
lower regression line represents weekend usage. The regression statistics
are as follows:
We attempted to determine a long-term historical relationship between
weather and energy use by comparing monthly temperature averages to our
monthly energy use data. We saw little or no correlation between electricity
and monthly temperature averages. (Note there is also little variation
in this data San Francisco monthly temperature averages between 1991
and 1996 ranged approximately between 50 and 65 degrees Fahrenheit.) A
heating slope was observed in steam consumption data.
Operational Findings from Initial IMDS Data
In this section we review results from the first few days of data collected
in early May 1998. These graphs were developed by the project team and
were not initially shared with the on-site staff because we were examining
how the staff would use the IMDS on their own. These results will be shared
with them later in Phase 3. The graphs are screen shots from Electric Eye,
the data visualization software used by the on-site operator.
Whole Building and Major End-Uses. The whole-building and major
end-use data provide an overview of major operating trends (Figure 48).
The graph shows whole-building power, total cooling (chillers, pumps, towers,
and air handlers), total lighting, and plug loads, all in area normalized
units (W/sqft). The remainder is additional miscellaneous loads such as
elevators, plus zone fans such as variable-air-volume boxes. This most
dramatic pattern is the sharp drop off of power each day at 6:00 PM. This
reflects good tracking of tenant schedules and needs. Most of this reduction
is due to effective HVAC management. Another interesting observation is
that the lighting load does not exceed 1.1 W/sqft, and the plug load is
less than 0.7 W/sqft. This is valuable information for design of new buildings
or ducting systems where HVAC systems are typically sized to meet combined
lighting and plug loads greater than 5 W/sqft.
Figure 48. Preliminary Whole Building and Major End Use DataClick for Figure 4-8
Figure 410. Preliminary Cooling System Data Chillers in OperationClick for Figure 4-10
Cooling System and Chillers. The chillers are the heart of the cooling system. Ensuring that they run at peak performance is critical to optimal energy use. The two chillers in the 160 Sansome building are over 20 years old and are rated at 225 tons each. During these few days the chillers meet their specified efficiency. However, the chillers are less efficient when they operate below 100 tons, which is less than 45% of their rated capacity (Figure 411). During the first few days of monitoring (during May, 1998), the chilled water loads were well below the rated capacity of the chillers, requiring 1 to 2 kW/ton for the majority of the time. A good practice benchmark of 0.45 kW/ton is shown for reference. It is also important to examine the combined plant efficiency. The efficiency of the combined system is twice that of the chiller, or the chiller accounts for about half of the power of the cooling system. The tower, pumps and air handling fans account for the other half. Any efforts to improve efficiency of the whole cooling system will have to include those components of the system. Again a benchmark of 0.6 kW/ton for the total plant efficiency is shown for reference. (Note that the cooling plant efficiency capping at 3.0 is an error due to limits on the individual points, and has been corrected.)
Figure 411. Preliminary Cooling System Operation Graph 1Click for Figure 4-11
One dramatic finding from the monitoring was the chiller turn on time. It appears that the chiller was coming on each morning at 7:30am for 15 minutes and then staying off for the rest of the day. This was the result of a recent control programming change. In fact on those days, the chiller should have never have come on at all (Figure 412). The chiller was coming on without any load, which could have resulted in a major failure. The other problems shown in Figure 412 are further described below.
The IMDS also showed a problem with controlling water flow though the chillers. When chiller 1 was off, the chilled water temperature responded to chiller 2 operation (Figure 413). This may be the result of chilled water was flowing through chiller 1 and that the back flow preventer or check valve was not operating correctly. This could be corrected by service of the check valve. This problem results in a low temperature boost across the evaporator. The chillers end up working harder (higher kW) for the same amount of cooling (tons), resulting in a poorer efficiency (high kW/ton). This also cuts the capacity of the chillers so the second chiller is brought on-line sooner than needed, which also increases chilled water and condenser water pumping energy.
Figure 413. Preliminary Cooling System Operation Graph 3Click for Figure 4-13
Cooling Towers. Cooling towers use a small portion of the total energy of a cooling plant. However, their operation can have a large impact on chiller energy use. It is common to operate towers to produce condenser water 10°F warmer than what is optimal. For each degree that the condenser water temperature is too high, there is a 1.2% degradation in chiller efficiency. Therefore the 10° F can be translated into 12% efficiency improvement in the chillers. At 160 Sansome the tower is controlled to supply approximately 75° F condenser water. On the day displayed in Figure 414, the wet bulb temperature averaged about 55° F, while the tower was supplying 75° F condenser water. The chiller should be able to operate at condenser water temperatures as low as 55 degrees (this should be re-verified with the manufacturer). This can be corrected through changes to the central plant controls.
Figure 414. Preliminary Cooling Tower Operation Graph 1Click for Figure 4-14
In addition to the high condenser water temperatures, the towers tend to cycle excessively, creating additional wear on the tower fan motors (Figure 415). One remedy for this problem would be to use variable speed drives on the tower fans. Operators could also adjust control algorithms to increase the on/off temperature band and should definitely use both cells with one chiller to improve the energy efficiency of the cooling plant.
Figure 415. Preliminary Cooling Tower Operation Graph 2Click for Figure 4-15
A more dramatic problem was found in the condenser water system. In chiller 2 the design flow is 615 gpm. The measured flow was 60% below the design flow (Figure 418). While increasing the condenser water flow will consume more pumping energy, it will make the chillers operate more efficiently. More flow and better heat exchange in the condenser of the chiller should improve the chiller efficiency and reduce the energy consumed by the chiller.
Section 1. Project Overview
Section 2. Pilot Site Selection and Technology
Innovation Findings
Section 3. IMDS Description and Accuracy
Section 4. Building Performance and Findings
from the IMDS
Section 5. Automation of Diagnostics
Section 6. Economic Issues and Related Technology
Section 7. Conclusions and Future Plans
Section 8. References
Appendix A. Web-Based Performance Analysis Tools
Appendix B. Diagnostic Plots
Appendix C. IMDS Points, Sensors, and Data
Production Systems
Appendix D. IMDS Findings Report Log